Progress report on Taigene complex building

2021-03-25

Five months have passed since the opening of the Taigene complex building. Time flies. At present, the construction of the main structure has been completed. At this stage, the task is to build wall masonry, as well as hydropower installation projects. Strive for completion by the end of 2021.

k8凯发(中国)天生赢家·一触即发

k8凯发(中国)天生赢家·一触即发

During the period, Taigene drawings made a major change, the original plan of the second floor canteen to the first floor, convenient for restaurant staff to transport vegetables and sundries. The follow-up work of the comprehensive building is the installation of elevators, the preparation of canteen equipment, the installation of office air conditioning, the introduction of natural gas in the canteen, the decoration and construction of indoor and outdoor walls, and the final acceptance procedures.

k8凯发(中国)天生赢家·一触即发

k8凯发(中国)天生赢家·一触即发

网站地图
友情链接:k8凯发天生赢家  z6com人生就是博  K8凯发  人生就是博  bwin必赢  4188云顶集团  k8凯发天生赢家  k8凯发官网  人生就是博官网  k8凯发天生赢家  k8国际  凯发一触即发  凯发一触即发  j9九游国际真人  Ag平台官方网站